“Goodeng Machine”GS12000-T Large series Hdd Machine helped finish——China-Russia Natural Gas Pipeline East line-New Chaobai River (Φ1219mm×1256m)successfully!
Project Name:China-Russia Natural Gas Pipeline East line-New Chaobai River Project
Construction Party:Zhejiang Yiwu Hengdong Municipal Engineering Company;
Project Characteristics:Tangshan-Badi Φ1219mm×1256m(steel pipe)New chaobai river directional crossing project
Geological Conditions:the entry and exit points are black clay, and the crossing strata are mostly River silt and sand layer
Construction difficulties:The geological conditions of river bottom are complex, the quicksand and silt are heavy, and the hole expansion is difficult
Malaysia Kuching City Central Wastewater Management System P2
Project overview: The drive span of this section is 240 meters, and the rock UCS is 100-120Mpa. The working shaft is 35 meters deep with high groundwater.
Construction difficulties: Deep cover depth, high rock UCS, and large wear coefficient, requiring high wear resistance for the cutters and the cutterhead.
Equipment: T10 enhanced Tangxing HRC-1500 rock pipe jacking machine